New Build

As a result of £25 million investment, the new Academy, sponsored by The SchoolsCompany Trust, will benefit from a new three-storey school building and four-court sports hall, built by the team at Kier.
The Goodwin Academy is a unique and very special school. We are immensely pleased and proud to have been awarded this new build and to have had the opportunity to develop an education vision which meets the needs, desires, talents and abilities of all our students not just now but importantly, in the future too.
“We are being entrusted with a very remarkable task and responsibility for all young people in Deal and for the town and we take that very seriously. We will have a school which enables us to continue to build on our strengths and ambitions for all our young people. They are after all at the heart of everything we do. We are creating a school of learning excellence for now and the future.”

Principal

  1. Phase one complete summer 2017
  2. College Decant to new Buildings summer 2017
  3. Demolition of the existing Buildings [Phase Two] summer 2017
  4. Followed by the landscaping works
  5. Phase two works complete early 2018

School contact: J Thompson, jthompson@goodwinacademy.org.uk
Kier contact: J Parnell, Jack.Parnell@kier.co.uk